Location
Toledo, OH
Timeline
2016 – 2018
Contract Value
$12.5M
TIS Role
Construction Engineering & Inspection
Client
ODOT District 2
True Inspection Services received the Construction Engineering and Inspection services contract for Phase 2 of the Anthony Wayne Bridge — a $12.5M steel repair and painting project on the historic 1931 suspension bridge.
The Anthony Wayne Bridge, also known as the High Level Bridge, is a 3,218-foot-long suspension bridge in Toledo, OH spanning the Maumee River. The bridge was constructed in 1931 and connects Clayton Street to Woodville Road carrying Ohio State Routes 2, 51, and 65.
In 2016, for Phase 2, ODOT contracted with United Coating and Lining (UCL) to repair structural steel and paint the entire structure for $12.5M. TIS received the Construction Engineering and Inspection services contract. As the painting contractor performed the work cleaning the existing steel, TIS inspected the blasted surface for any coatings issues or structural issues. The structural issues included stress fractures, steel delamination and rivet loss.
TIS oversaw daily operations of staff, project schedules, reviewed change orders and force account documentation, managed materials, reviewed daily inspection reports, and attended progress and dispute resolution meetings. This project brought unique challenges given that it is over navigable waters where ships, including the Coast Guard, passed through.