New Ramp From 315 S. To I-270 E. AND U.S. 23
Transportation

New Ramp From 315 S. To I-270 E. AND U.S. 23

Location

Franklin County, OH

Timeline

2016 – 2017

Contract Value

$70M

TIS Role

Construction Inspection

Client

ODOT District 6

TIS provided construction inspection and daily documentation on the reconfiguration of the interchanges at IR 270 and SR 315 and IR 270 and US 23.

This project reconfigured the interchanges at IR 270 and SR 315 and IR 270 and US 23. The project includes the addition of lanes, storm sewer work, construction of bridges, traffic control, lighting, reconstruction of a bike path, and utility work.

New ramps were built from US 23 south to SR 315 to separate from the US 23 south to I 270 west ramp. The 'loop ramp' from SR 315 south to I-270 east was eliminated and a new 'flyover ramp' was built. A new bridge was built for SR 315 north traffic that goes to I-270 east and U.S. 23. About 1,000 feet of the Olentangy Trail was reconstructed underneath the new interstate ramps at I-270 and SR 315.

TIS provided construction inspection and daily documentation of work performed by the contractors and material testing on the construction project.