Tinkers Creek Bridge Replacement Project
Structures

Tinkers Creek Bridge Replacement Project

Location

Hudson, OH

Timeline

2024 – 2027

Contract Value

$41.9M

TIS Role

Construction Inspection & Engineering

Client

Ohio Turnpike & Infrastructure Commission

True Inspection Services is providing project engineering and construction inspection services as a subconsultant to Woolpert on this bridge replacement project — Ohio Turnpike's largest bridge project in 20 years.

This is Ohio Turnpike's largest bridge project in 20 years. The project consists of replacing two 25-span (963-foot) bridges over Tinkers Creek. Two lanes of traffic in each direction will be maintained throughout the duration of the project, while completely replacing both structures.

The new twin bridges will match the existing structure widths of 63 feet each with three lanes in both directions, spanning Tinkers Creek. The new design will be executed with a goal of shortening the existing almost 1,000-foot-long structures by as much as 40%.

Environmental concerns are important in this project, as the bridges are being built over a wetland and waterway. Innovative ground improvement methods are being used to construct embankments in areas of poor existing soils.